Time lines for approval of Bulk Connections at Various levels


Sl.No. Type of Approval Time Line in accordance with
1. Pre Scrutiny 3 working days from the date of receipt of application As per TG-ipass Guidelines
2. Feasibility Approval 14 working days from the date of pre scrutiny approval As per TG-ipass Guidelines
3. Issue of Demand Notice With 3 working days after feasibility approval As per Dept., Procedure
4. Amount to be paid 45 days from the receipt of the demand notice As per Dept., Procedure
5. Administrative Sanction 30 days after receipt of the amount As per Dept., Procedure
6. Giving Connection 90 days after Administrative sanction for works costing less than Rs. 10 lakhs works and 120 days for working costing above Rs.10 lakhs works. As per Dept., Procedure

List of External agencies, Third party agencies and Vendor list are given below

Search for Bulk water suply connections Approved to Firms/ Commercial establishments/ Industires etc over a period




Date Name of Firms / Establishments / Industries
2021-05-09 M/s Prajay Water front
2022-01-11 M/s MRF Limited
2022-02-24 M/s Sri Laxmi Narsimha Sevasharam
2022-06-05 M/s Mylan Laboratories Unit-7,
2022-07-07 M/s Trefoil Packaging Pvt.Ltd.
2022-08-22 Sairam Confectionary
2022-08-22 M/s AB Dairy
2022-09-20 Gayathri Institute of Technology and sciences
2022-09-20 M/s DC Development Hyderabad Limited,
2022-09-21 TSIIC-Food processing and Other Industrial Parks-Siddipet,Medak,&Medchal
2022-11-01 M/s Prompt Industries Pvt Ltd.
2022-12-01 M/s Arunjyothi Bio Venture Limited
2022-12-09 M/s Power Grid Corporation of IndiaLimited
2022-12-12 M/s Truksha Foods Pvt Ltd.
2022-12-12 M/s Zulfi Ravdjee
2022-12-15 M/s Central Industries
2023-01-12 M/s Astral Ltd
2023-01-16 Government Medical College , Thirumala Hills
2023-02-09 M/s.Commander Ali's Academy of Merchant Navy
2023-03-20 Green Industrial Park-TSIIC Polepally SEZ
2023-03-31 M/s Edoor Solution Pvt Ltd
2023-03-31 M/s Gayatri Doors Pvt Ltd,
2023-04-01 Sri Sankara Gurukula Veda Patasala
2023-04-12 M/s TCI Express Ltd
2023-04-28 M/s IT Towers
2023-04-29 M/s Ashirvad Pipes Pvt.Ltd
2023-05-20 M/s Welspun Advanced Materials (India) Limited
2023-05-20 M/s Lingampally Lakshma Reddy Gardens
2023-06-21 A S CASTINGS WORKS
2023-06-21 Telangana Special Food Processing Zone(TSFPZs)
2023-06-23 M/s Neha Medical Devices
2023-06-23 M/s Aegis Agro Chemicals India Pvt Ltd
2023-06-28 M/s Siri Indane Gramin Vitrak
2023-06-28 M/s Maram Mamatha Convention Hall
2023-07-03 CLEAN AIR TECHNOLOGIES
2023-08-28 M/S Bricmor Lahacienda Villas
2023-09-04 Valluripalli Radha Housing
2023-09-06 Cygnet Polymers Private Limited
2023-09-06 Encore Fabrics Pvt.Ltd
2023-10-05 DAIFUKU INTRALOGISTICS INDIA PVT.LTD
2023-10-20 M/s Toshiba Transmission & Distribution Systems (India) Pvt Ltd
2023-11-13 M/s Tata Coffee Limited
2023-11-14 M/s RVM College of Nursing
2023-11-21 M/s Anthea Pharma Private Limited
2023-12-11 M/s VR Organic Farms &, Dairy
2024-01-07 M/s MPL Steel Industries Private Limited
2024-01-10 M/s Organo, Kandawada(V)
2024-01-10 M/s Organo Damarigida(V)
2024-01-10 M/s Organo Antharam(V)
2024-01-12 M/s SVS Convention Hall
2024-01-18 M/s Shiva Balaji Cold Storage unit
2024-01-24 Railway Staff Quarters
2024-03-21 VIPIN STEEL UDYOG
2024-03-21 Bulk Water Connection to (8) firms through common line
2024-03-26 Telangana State Industrial Infrastructure Corporation Limited (MSME IP)
2024-04-24 SBMI GREEN ALUMINIUM PRIVATE LIMITED
2024-06-05 GM NEXUS INDIA PRIVATE LIMITED
2024-07-10 M/s CLEAN AIR TECHNOLOGIES

Note : - The data in this dashboard is updated on realtime basis.Last update